A Fast Solution To a Significant Housing Crisis
In February 2022, East Lismore, NSW, was hit by an unprecedented flood, forcing 10,000 people out of their homes and making 4000 homes uninhabitable. As a result, people had to find shelter in their cars, caravans, tents, garage floors, evacuation centres or live with family and friends.
Compounded by the housing crisis experienced prior to the flood, the community needed an innovative and urgent solution to get people into safe and secure housing. In response to the dire housing situation, a significant commitment of $285 million was made towards the implementation of a Temporary Housing Support Package, aimed at providing essential rental support and housing solutions for families adversely affected by the flood in the Northern Rivers region. A substantial portion of this funding, totalling $115 million, was allocated to the construction of six temporary housing villages. These villages were designed to offer a lifeline to the flood-impacted families in the region, offering them accommodation while their homes were either repaired or rebuilt.
Homes
732Week Production
10Insulated Panel
23km2Flashings
17klmPurlins
25klmThe Materials
Recognising the pressing need to respond promptly and effectively to the large number of displaced families, the NSW Department of Corrections and Community Services took on the challenge of finding a quick and scalable solution. Prefab temporary housing, akin to that utilised by mining companies for FIFO workers, emerged as an obvious solution to the problem.
The project was awarded to Hutchinson Builders (Hutchies) and Highline Roofing, partners of Ausdeck Building Systems (then Ausdeck Group). Having worked with Ausdeck on the QLD Government’s Wellcamp Facility, Hutchinson Builders had the confidence that Ausdeck could provide a one-stop-shop solution to supply the right materials for the job, fast.
The Execution
To ensure the rapid and efficient assembly of the prefab modular homes, Ausdeck delivered the building materials in kit form, ready for construction. In just 10 weeks, Ausdeck manufactured, packed, and delivered 23,000 m² of insulated panels, 17,000 l/m of flashings, 25,500 l/m of purlins, 2,700 l/m of lightweight beams, 2,700 l/m of gutter, and 2,000 l/m of powder-coated posts. The modular construction phase was a remarkable feat, encompassing the construction of 732 homes and attached patios in just five months.
Choosing a product that was quick and easy to install was a key criterion for the construction of the modular homes. Ausdeck’s insulated roofing panel was selected for its versatile, custom-manufactured, all-in-one design, serving as roofing, insulation, and ceiling in one solution. Its user-friendly tongue and groove joining system, impressive spans, and excellent thermal properties made it an ideal product for the modular project.
The Result
Ausdeck’s swift manufacturing, precise packaging, and timely delivery capabilities played a pivotal role in the successful completion of the East Lismore housing project. This project exemplifies Ausdeck’s commitment to providing efficient solutions in critical situations, making us a preferred partner for major endeavours requiring precision and speed.
Project Video
Other Projects

Golden Beach Gable Patio Project
Discover how a stylish, spacious verandah extension, constructed with coastal-grade materials elevated the lifestyle of this Golden Beach family. A notable trend has emerged towards expanding outdoor living spaces in the relaxing and peaceful coastal suburb of Gold Beach, Queensland.
View ProjectContact your local rep
Our team is on standby to help you put your project together. Just get in touch with our specialist today.